steps icon Step 6 | IPT finalization of DIDs/CDRLs


Step 6 is the key step in this process. From the WBS, and going through a Data Call and a DRRB, the IPT will then finalize all the tailored DIDs/CDRLs. Therefore, at the end of Step 6 the Program Office has identified the exact data that is required for the entire life cycle of the program in terms of sustainment, competition, and the delivery of the data.

Section J is the attachment to the Statement of Work. One of the important attachments from a data deliverable perspective is the CDRLs, DD Form 1423 as an Exhibit.

ipt finalization of dids cdrls

dfars icon Click to open the DFARS Clause and Provision for Data Prices

info icon

The IPT updates the draft Statement of Work including listing all the CDRLs as an Exhibit



Click below to proceed to the next step.

path Step 7 | IPT Reviews Data Right Markings