step icon Step 23 | Blocks 10, 11, 12 and 13


Blocks 10-13 are focused on final delivery from the contractor the “WHEN” for CDRL frequency, data collection dates, and submittal. If Block 8 indicates that a draft is required for approval, review/turn around should be described in Block 16, with block 12 being reserved for the approved copy.

Draft delivery dates specified in block 16 must allow review and turn around time to meet the Block 12 requirement. CDRL preparers should use the codes as noted in DoD 5010.12-M to the maximum extent possible for clarity. Only use Block 16 in order to amplify information in Blocks 10 - 13, if necessary, to avoid ambiguity.

blocks 10, 11, 12 and 13